Project

Lydstep Farm fire damage

Sector

Insurance reinstatement - fire damage

Duration

40 weeks

Contract value

£260k

Project overview

Lydstep Farm experienced significant fire damage, leading to a large contract for Certus Construction in the insurance sector. The project involved replacing the entire roof and carrying out internal refurbishments, acting as the principal contractor throughout.

A complex scaffold was erected to protect the building during roof replacement. The internal refurbishment included demolishing and reconstructing much of the first floor.

Key reinstatement works included installing new roof trusses, partitions, doors, central heating system, electrical works, 3 new bathroom suites, hardwood flooring and full decoration.

Working closely with both the homeowner and loss adjustor throughout, we delivered a high-end finish in line with the homeowner’s choices and specifications

Scope of works

  • Erect complex scaffolding with top hat
  • Install new roof structure and coverings
  • Complete internal refurbishment, including 3 new bathrooms
  • Decorations and surface repairs throughout

Words from the client

“This was a challenging project involving complex scaffolding and restricted access to site for lifting equipment and cranes. Certus finished the internal work to an extremely high standard to meet the demands of the client.”

AndySurveyor