Certus was contracted to carry out a refurbishment to a ground floor property in Castleford, including supply and installing a new kitchen
- Client: Aspray Ltd
- Duration: 3 Weeks
- Contract Value: Circa 24k
The homeowners dryer suffered an electrical fault causing a fire in the existing kitchen, we were appointed to put the place back together.
The works involved:
- Removal of all existing
- Partial rewire
- Plastering
- Install new kitchens
- Install new floors
- Install new external doors and windows
- Second fix joinery
- Decorations